Dalian Heavy Industry's Sheyang base wind tower intelligent manufacturing project, which started construction in March 2023 and began trial production in July 2023, is now in the acceptance phase and will fully commence production after passing. The project will meet an annual production capacity of 150,000 tonnes of wind tower manufacturing.
“项目于2023年3月上旬启动施工建设,历时4个月完成了原厂房改造、新建工程施工建设和设备安装调试,于2023年7月下旬开始进行试生产。”chinapower.com.cn