Boom Supersonic opens $150M turbine factory in Centennial, Colorado
Boom Supersonic unveiled a $150 million campus near Centennial Airport on October 22, 2026, spanning nearly 200,000 square feet. The factory will produce 42 MW natural gas turbines for data centers, with first deliveries targeted for mid-2027.
Capacity
25 turbines per year by 2028, 50 by 2029
Products42 MW natural gas turbines
“ground power first”industrialsage.com
- 2 sources
- industrialsage.comBoom Supersonic Turbine Factory: Power Before PlanesNov 2, 2026