# GE Vernova to supply gas turbines for Qurayyah power plant expansion

GE Vernova secured an order for five 7H-Class gas turbines (three 7HA.03 and two 7HA.02) from Técnicas Reunidas and Orascom Construction for the 3 GW Qurayyah IPP expansion project in Saudi Arabia's Eastern Province.

- Type: Contract
- Announced: 2025-05-28
- Where: Eastern Province, Saudi Arabia, Saudi Arabia
- Value: $14.2B
- Status: announced
- Capacity: 3 GW
- Products: 7HA.03 gas turbines, 7HA.02 gas turbines
- Sectors: [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md)

## Companies

- [GE Vernova](https://endata.com/companies/2947.md)
- [Tecnicas Reunidas](https://endata.com/companies/2001.md) (customer)
- [GE Vernova](https://endata.com/companies/2947.md) (supplier)
- [Orascom Construction](https://endata.com/companies/8450.md) (customer)
- [Orascom](https://endata.com/companies/27038.md) (customer)

## Sources

- [gevernova.com](https://www.gevernova.com/news/press-releases/ge-vernova-h-class-gas-turbines-expand-qurayyah-power-plant-saudi-arabia), 2025-05-28: "GE Vernova today announced it has secured an order for five 7H-Class gas turbines - three 7HA.03 and two 7HA.02 units from Técnicas Reunidas and Orascom Construction."
- [solarquarter.com](https://solarquarter.com/2025/05/29/ge-vernova-lands-major-turbine-deal-for-saudi-arabias-3-gw-qurayyah-power-project/), 2025-05-29: "GE Vernova announced it has received an order for five 7H-Class gas turbines—three 7HA.03 and two 7HA.02 units—for the Qurayyah Independent Power Plant (IPP) Expansion Project in Saudi Arabia."
- [meed.com](https://www.meed.com/ge-vernova-wins-gas-turbines-order-on-26bn-saudi-ipp-project), 2025-05-31: "The order for five 7H-class gas turbines for the Qurayyah independent power plant expansion project in the Eastern Province has been placed by the main EPC contractors – Tecnicas Reunidas and Orascom"
- [petropipefze.com](https://petropipefze.com/ge-vernova-secures-order-for-five-7h-class-gas-turbines-from-tecnicas-reunidas-and-orascom-construction/), 2025-06-02: "We have developed a productive and successful relationship with TR & ORASCOM CONSTRUCTION building on our proven expertise in natural gas combined cycle plant engineering, operability, and plant integration."
- [gasturbineworld.com](https://gasturbineworld.com/ge-vernova-orders-keep-piling-on/), 2025-06-07: "GE Vernova did well from President Trump’s recent visit to Saudi Arabia, announcing initiatives worth up to $14.2 billion for energy equipment technology and services to support power generation and grid stability projects."

---
Data from Endata (https://endata.com/). Announcements are summarized from public sources and may be incomplete; check the linked originals.