# SEPCOIII installs first GE 7HA.03 gas turbine at Taiba 1 power plant in Saudi Arabia

SEPCOIII Electric Power Construction Co., Ltd. installed the first GE Vernova 7HA.03 gas turbine at the Taiba 1 IPP project in Saudi Arabia. The turbine is part of a 1.8 GW power plant expected to deliver electricity by 2027.

- Type: Contract
- Announced: 2025-05-08
- Where: 100 km southeast of Madinah, Saudi Arabia
- Status: under construction
- Capacity: 1.8 GW
- Products: 7HA.03 gas turbine, electricity
- Sectors: [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md)

## Companies

- [SepcoIII Electric Power Construction Company](https://endata.com/companies/30607.md)
- [GE Vernova](https://endata.com/companies/2947.md) (supplier)

## Sources

- [utilitybusinessmena.com](https://www.utilitybusinessmena.com/electricity/sepcoiii-installs-saudi-arabias-first-ge-7ha-03-gas-turbine-at-taiba-1-power-plant), 2025-05-08: "SEPCOIII Electric Power Construction Co., Ltd. (SEPCOIII), the engineering, procurement, and construction (EPC) contractor for the Taiba 1 Independent Power Producer (IPP) project, has successfully installed the first 7HA.03 gas turbine."

---
Data from Endata (https://endata.com/). Announcements are summarized from public sources and may be incomplete; check the linked originals.