# BHEL secures ₹8,000 crore order from Mahagenco for Koradi thermal power plant

BHEL received a Letter of Award from Mahagenco on February 7, 2025, for a 2x660 MW boiler turbine generator package at Koradi Thermal Power Station in Nagpur, Maharashtra, worth ₹8,000 crore.

- Type: Contract
- Announced: 2025-02-07
- Where: Nagpur, Maharashtra, India
- Value: $920.0M (80.0B INR)
- Status: announced
- Capacity: 1320 MW
- Products: boiler turbine generator
- Sectors: [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md)

## Companies

- [Bharat Heavy Electricals](https://endata.com/companies/1451.md)
- [Bharat Heavy Electricals](https://endata.com/companies/1451.md) (supplier)
- [Gujarat State Electricity Corporation Limited](https://endata.com/companies/10634.md) (customer)
- [Adani Energy Solutions](https://endata.com/companies/13845.md) (investor)
- [Singareni Collieries Co Ltd](https://endata.com/companies/17764.md) (customer)
- [Maharashtra State Power Generation Company](https://endata.com/companies/29420.md) (customer)
- [Hitachi Energy India](https://endata.com/companies/62817.md) (partner)
- [Damodar Valley Corporation](https://endata.com/companies/63137.md) (customer)
- [Rajasthan Part I Power Transmission](https://endata.com/companies/82857.md) (customer)

## Sources

- [thehindu.com](https://www.thehindu.com/business/Industry/bhel-secures-8000-crore-order-from-mahagenco/article69197220.ece), 2025-02-08: "BHEL received the Letter of Award from MAHAGENCO on February 7, 2025, for the BTG package of Koradi Thermal Power Station in Nagpur district of Maharashtra."
- [power-technology.com](https://www.power-technology.com/news/bhel-wins-914m-mahagenco-contract/), 2025-02-10: "BHEL received the letter of award from Mahagenco on 7 February 2025, with completion expected within 52 to 58 months."
- [tndindia.com](https://www.tndindia.com/bhel-wins-letter-of-intent-for-rs-6200-crore-dvc-mandate/), 2025-02-12: "Won in an international competitive bidding process, the contract involves supply, erection, testing & commissioning of: steam generators and auxiliaries."
- [outlookbusiness.com](https://www.outlookbusiness.com/industry/bhel-bags-order-to-install-boiler-package-at-raghunathpur-thermal-plant), 2025-02-13: "BHEL has secured a significant order for installing the steam generator (boiler) island package based on supercritical technology at the 2x660 MW Raghunathpur Thermal Power Station (TPS) Phase-II."
- [cablecommunity.com](https://cablecommunity.com/bhel-wins-%e2%82%b98000-crore-order-from-mahagenco-for-1320-mw-power-plant/), 2025-02-14: "Bharat Heavy Electricals Ltd (BHEL), the largest government-owned electrical/ industrial technology company, has won a Rs. 8,000 Crore order from Maharashtra State Power Generation Company Ltd. (Mahagenco)."
- [ndtvprofit.com](https://www.ndtvprofit.com/business/bhel-wins-rs-6700-crore-singareni-thermal-power-project-contract-9956491), 2025-02-14: "Bharat Heavy Electricals Ltd. secured a letter of intent from Singareni Collieries Company Ltd. for the engineering, procurement, and construction package for the Singareni Thermal Power Project, Stage II (1x800 megawatt) at Mancherial district, Telangana, India."
- [themachinemaker.com](https://themachinemaker.com/news/bhel-secures-boiler-contract-for-raghunathpur-thermal-power-plant-expansion/), 2025-02-15: "BHEL has announced the successful acquisition of an order to supply and install the steam generator (boiler) island package for Phase-II of the 2×660 MW Raghunathpur Thermal Power Station."
- [energy.economictimes.indiatimes.com](https://energy.economictimes.indiatimes.com/news/power/bhel-bags-rs-7500-cr-order-to-set-up-800-mw-unit-at-ukai-plant-in-gujarat/119296217), 2025-03-21: "The unit will start commercial operation within 54 months."

---
Data from Endata (https://endata.com/). Announcements are summarized from public sources and may be incomplete; check the linked originals.