# ELSiB completes testing of 130 MW turbogenerator for Novosibirsk TPP-3

ELSiB completed acceptance tests of a 130 MW hydrogen-cooled turbogenerator, the first of two manufactured for Novosibirsk TPP-3 under the DPM-2 modernization program. The equipment will be shipped by end of February 2025.

- Type: Product launch
- Announced: 2024-12-17
- Where: Novosibirsk, Russia, Russia
- Status: completed
- Capacity: 130 MW
- Products: hydrogen-cooled turbogenerator
- Sectors: [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md)

## Companies

- [ELSIB](https://endata.com/companies/34349.md)
- [Siberian Generating Company](https://endata.com/companies/51414.md) (customer)