# Prysmian and DEME win $1.8 billion balance of plant contract for Dominion Coastal Virginia Offshore Wind

A Prysmian and DEME Group consortium was awarded the balance of plant contract by Dominion Energy Virginia for the Coastal Virginia Offshore Wind project, worth about $1.8 billion in total, of which about $730 million relates to Prysmian. Completion is expected by 2026.

- Type: Contract
- Announced: 2023-06-09
- Where: Virginia Beach, Virginia offshore, United States
- Value: $1.80B
- Status: announced
- Capacity: 176 turbines; approximately 348 miles of export cable and 198 miles of inter-array cable
- Products: HVAC export cables, inter-array cables, offshore foundations, substations
- Sectors: [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md), [Electrical Equipment](https://endata.com/sectors/electrical-equipment.md)

## Companies

- [Prysmian](https://endata.com/companies/968.md) (supplier)
- [DEME](https://endata.com/companies/1289.md) (partner)
- [Dominion Energy Virginia](https://endata.com/companies/10662.md) (customer)

## Sources

- [na.prysmian.com](https://na.prysmian.com/insight/sustainability/prysmian-group-secures-dominion-energy-730-m-dollars-submarine-cable-project), 2023-06-09: "The total value of the contract is approximately $1.8 billion, of which around $730 million is related to Prysmian for the cable supply and the installation works under its responsibility."

---
Data from Endata (https://endata.com/). Announcements are summarized from public sources and may be incomplete; check the linked originals.