# Baker Hughes wins Bechtel contract to supply turbines and compressors for Port Arthur LNG Phase 1

Baker Hughes won a contract from Bechtel to supply four Frame 7 turbines, eight centrifugal compressors and two electric motor driven compressors for the first phase of Sempra's Port Arthur LNG project in Texas. The deal was announced on Monday, March 27, 2023, after Sempra's final investment decision on March 20. The price was not disclosed.

- Type: Contract
- Announced: 2023-03-27
- Where: Port Arthur, Texas, United States
- Status: announced
- Capacity: Two liquefaction trains with total capacity of about 13 million tonnes per annum (project)
- Products: Frame 7 gas turbines, centrifugal compressors, electric motor driven compressors
- Sectors: [Industrial Machinery](https://endata.com/sectors/industrial-machinery.md)

## Companies

- [Baker Hughes](https://endata.com/companies/1895.md) (supplier)
- [Bechtel](https://endata.com/companies/2657.md) (customer)
- [Sempra Infrastructure](https://endata.com/companies/10391.md) (partner)

## Sources

- [lngprime.com](https://lngprime.com/americas/baker-hughes-clinches-port-arthur-lng-gig/77253/), 2023-03-28: "Baker Hughes has won a contract from Bechtel to supply two liquefaction trains for the first phase of Sempra's Port Arthur LNG export project in Texas."

---
Data from Endata (https://endata.com/). Announcements are summarized from public sources and may be incomplete; check the linked originals.