# Voltamp Transformers to build new power transformer plant near Vadodara, India

Voltamp Transformers plans to build a new power transformer manufacturing facility near Vadodara, Gujarat, with an annual capacity of 6,000 MVA in the first phase. The capital outlay is around ₹200 crore, and completion is expected by July 2026.

- Type: New facility
- Announced: 2024-07-31
- Where: near Vadodara, Gujarat, India
- Value: $24.0M (2.00B INR)
- Starts operating: Jul 2026
- Status: announced
- Capacity: 6,000 MVA per annum (first phase)
- Products: power transformers up to 250 MVA, 220kV class
- Sectors: [Electrical Equipment](https://endata.com/sectors/electrical-equipment.md)

## Companies

- [Voltamp Transformers](https://endata.com/companies/57528.md)

## Sources

- [tndindia.com](https://www.tndindia.com/voltamp-expects-to-complete-new-transformer-facility-by-mid-2026/), 2024-07-31: "With increase demand for electricity and transformers projected over the next 5 to 6 years period, it has become imperative to enhance manufacturing capacity."
- [transformer-magazine.com](https://transformer-magazine.com/news/voltamp-to-complete-new-facility-in-2026/), 2024-08-01: "As an increase in demand for electricity and transformers has been projected over the next 5 to 6 years period, it has become imperative to enhance manufacturing capacity."

---
Data from Endata (https://endata.com/). Announcements are summarized from public sources and may be incomplete; check the linked originals.