# GE Vernova to supply gas turbines for Taiba 1 and Qassim 1 power plants in Saudi Arabia

GE Vernova has secured a contract from SEPCOIII to deliver six 7HA.03 and two 7E.03 gas turbines for the Taiba 1 and Qassim 1 combined-cycle power plants in Saudi Arabia, which have a combined capacity of up to 3.8 GW. GE Vernova also signed a 21-year service agreement with NOMAC for the plants.

- Type: Contract
- Announced: 2024-06-25
- Where: Taiba 1: ~100 km southeast of Madinah; Qassim 1: ~30 km southeast of Buraydah, Saudi Arabia
- Status: announced
- Capacity: 3.8 GW combined
- Products: gas turbines, power plant services
- Sectors: [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md)

## Companies

- [GE Vernova](https://endata.com/companies/2947.md) (supplier)
- [ACWA Power](https://endata.com/companies/5576.md) (partner)
- [Saudi Electricity Company](https://endata.com/companies/8447.md) (partner)
- [SepcoIII Electric Power Construction Company](https://endata.com/companies/30607.md) (customer)
- [NOMAC](https://endata.com/companies/78238.md) (customer)

## Sources

- [nsenergybusiness.com](https://www.nsenergybusiness.com/news/ge-vernova-wins-gas-turbine-contract-for-taiba-1-and-qassim-1-power-plants/), 2024-06-25: "We are delighted to team with SEPCOIII and ACWA Power’s NOMAC to deploy our most advanced power generation technologies."

---
Data from Endata (https://endata.com/). Announcements are summarized from public sources and may be incomplete; check the linked originals.