# Airbus Tianjin A320 second assembly line foundation completed

The foundation of the main assembly building for Airbus' second A320 family final assembly line in Tianjin, China, has been completed. The project is on track for delivery and production start in July 2025, with full completion by December 2026.

- Type: Expansion
- Announced: 2024-03-31
- Where: Tianjin, China, China
- Starts operating: Jul 2025
- Status: under construction
- Products: A320, A321 aircraft
- Sectors: [Automotive Components](https://endata.com/sectors/automotive-components.md)

## Companies

- [Airbus](https://endata.com/companies/1653.md)

## Sources

- [chinanews.com.cn](http://www.chinanews.com.cn/cj/2024/03-31/10190649.shtml), 2024-03-31: "计划2025年7月总装厂房实现交付投产，2026年12月全部交付投产。"

---