# Mitsubishi Power receives order for Navoi 3 power plant in Uzbekistan

Mitsubishi Power has received an order from JSC Thermal Power Plants for one system of core equipment, including an M701JAC gas turbine, for the 600 MW Navoi 3 GTCC power plant in Uzbekistan. Commercial operation is scheduled to start in 2026.

- Type: Contract
- Announced: 2024-03-27
- Where: Navoi, Uzbekistan, Uzbekistan
- Status: announced
- Capacity: 600 MW electric power, 200 Gcal/h heat
- Products: gas turbine combined cycle equipment, M701JAC gas turbine, steam turbine, generator
- Sectors: [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md)

## Companies

- [Mitsubishi Power](https://endata.com/companies/7073.md)
- [Mitsubishi Heavy Industries](https://endata.com/companies/493.md) (investor)
- [Mitsubishi Electric](https://endata.com/companies/2378.md) (partner)
- [JSC Thermal Power Plants](https://endata.com/companies/75629.md) (customer)

## Sources

- [electricalindia.in](https://www.electricalindia.in/mitsubishi-power-receives-order-for-uzbekistan-navoi-3-power-plant-project/), 2024-03-27: "Mitsubishi Power has received an order for one system of core equipment for a high-efficiency power generation facility for the third facility planned to be built at the Navoi Power Plant (Navoi 3) by JSC Thermal Power Plants."

---