# Doosan Enerbility wins $210M contract for Andong power plant

Doosan Enerbility signed a 280 billion won ($209.6 million) contract with Korea Southern Power Co. to supply a gas turbine, steam turbine and heat recovery steam generator for a combined cycle power plant in Andong, South Korea. The plant is expected to be completed in December 2026.

- Type: Contract
- Announced: 2024-01-25
- Where: Andong, North Gyeongsang Province, South Korea, South Korea
- Value: $209.6M
- Status: announced
- Capacity: 380 MW gas turbine, 569 MW total plant capacity
- Products: gas turbine, steam turbine, heat recovery steam generator
- Sectors: [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md)

## Companies

- [Doosan Enerbility](https://endata.com/companies/9315.md) (supplier)
- [Korea Southern Power](https://endata.com/companies/20366.md) (customer)

## Sources

- [kedglobal.com](https://www.kedglobal.com/us/energy/newsView/ked202401250016), 2024-01-25: "We plan to expand the collaboration to long-term gas turbine maintenance service to enhance the domestic gas turbine industry's capabilities in all fields and actively seek an entry into the global market."
- [kedglobal.com](https://www.kedglobal.com/energy/newsView/ked202401250016), 2024-01-25: "We plan to expand the collaboration to long-term gas turbine maintenance service to enhance the domestic gas turbine industry's capabilities in all fields and actively seek an entry into the global market."

---