# Doosan Enerbility wins $2.1B contract for Andong combined cycle power plant main equipment

Doosan Enerbility signed a 280 billion won ($2.1 billion) contract with Korea Southern Power Co. to supply main equipment including a 380MW H-class gas turbine, steam turbine, and HRSG for Unit 2 of the Andong combined cycle power plant in Andong, Gyeongsangbuk-do, South Korea. The plant is scheduled for completion in December 2026.

- Type: Contract
- Announced: 2024-01-25
- Where: Andong, Gyeongsangbuk-do, South Korea
- Value: $2.10B
- Status: announced
- Capacity: 569 MW
- Products: 380MW H-class gas turbine, steam turbine, heat recovery steam generator (HRSG)
- Sectors: [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md)

## Companies

- [Doosan Enerbility](https://endata.com/companies/9315.md)
- [Korea Southern Power](https://endata.com/companies/20366.md) (customer)

## Sources

- [mk.co.kr](https://www.mk.co.kr/news/business/10929255), 2024-01-25: "두산에너빌리티는 한국남부발전과 2800억 원 규모의 안동복합발전소 2호기 주기기 공급계약을 체결했다고 밝혔다."

---
Data from Endata (https://endata.com/). Announcements are summarized from public sources and may be incomplete; check the linked originals.