# Hitachi Energy wins order for SuedLink DC4 HVDC Light link in Germany

Hitachi Energy won a major order from TenneT and TransnetBW to supply HVDC Light converter stations and cable section stations for the 2,000 MW SuedLink DC4 interconnection, announced August 3, 2022.

- Type: Contract
- Announced: 2022-08-03
- Where: Germany
- Status: announced
- Capacity: up to 2,000 megawatts
- Products: HVDC Light converter stations, HVDC cable section stations
- Sectors: [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md), [Electrical Equipment](https://endata.com/sectors/electrical-equipment.md)

## Companies

- [TenneT](https://endata.com/companies/272.md) (customer)
- [Hitachi ABB Power Grids](https://endata.com/companies/8446.md) (supplier)
- [TransnetBW](https://endata.com/companies/9536.md) (customer)

## Sources

- [globenewswire.com](https://www.globenewswire.com/news-release/2022/08/03/2491051/0/en/Hitachi-Energy-supports-huge-step-in-Germany-s-energy-transition.html), 2022-08-03: "Hitachi Energy today announced it has won a major order from TenneT and TransnetBW, two of Germany's four transmission system operators."

---