# Uniboard proceeds with $350M modernization of Val-d'Or particleboard plant

Uniboard announced that the third phase of its modernization program for its particleboard and TFL mill in Val-d'Or, Quebec, is on track. The $350 million project includes a new distribution complex (operational August 2023) and a new continuous press line (expected Q1 2025), expanding annual particleboard capacity from 360,000 to 550,000 m³.

- Type: Expansion
- Announced: 2023-06-06
- Where: Val-d'Or, Quebec, Canada
- Value: $350.0M
- Starts operating: Q1 2025
- Status: under construction
- Capacity: 550,000 m³ per year (310 million square feet)
- Products: particleboard, thermally fused laminates
- Sectors: [Construction Materials](https://endata.com/sectors/construction-materials.md)

## Companies

- [Uniboard Canada Inc.](https://endata.com/companies/63605.md)

## Sources

- [uniboard.com](https://www.uniboard.com/en/news/uniboard-val-d-or-particleboard-plant-modernization-program-going-to-plan), 2023-06-22: "Uniboard broke ground on Phase 3 in September of 2022."

---
Data from Endata (https://endata.com/). Announcements are summarized from public sources and may be incomplete; check the linked originals.