# SaskPower selects Black & Veatch and Graham Construction for gas turbine additions

SaskPower awarded a joint venture of Black & Veatch and Graham Construction a contract to build two 46 MW simple cycle gas turbines at the Ermine and Yellowhead power stations in Saskatchewan, Canada.

- Type: Contract
- Announced: 2023-06-02
- Where: near Kerrobert and near North Battleford, Saskatchewan, Canada
- Status: announced
- Capacity: 46 MW each (two units)
- Products: simple cycle gas turbines
- Sectors: [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md)

## Companies

- [Black & Veatch](https://endata.com/companies/293.md) (supplier)
- [SaskPower](https://endata.com/companies/27686.md) (customer)
- [Graham Construction](https://endata.com/companies/53500.md) (supplier)

## Sources

- [power-eng.com](https://www.power-eng.com/gas/turbines/saskpower-selects-black-veatch-graham-construction-to-add-new-gas-turbines-at-two-plants/), 2023-06-02: "SaskPower has selected a joint venture between Black & Veatch and Graham Construction to build two 46 MW simple cycle gas turbines at the Ermine Power Station... and at the Yellowhead Power Station..."

---