# Mitsubishi Power to supply gas turbines for 1.6 GW peaking plant in Brazil

A consortium of Mitsubishi Power Americas and CONSAG signed an EPC agreement with Portocem Geração de Energia for the Portocem Thermoelectric Power Plant in Brazil. Mitsubishi Power will supply four M501JAC gas turbines for the 1.6 GW plant, with groundbreaking on May 5, 2023.

- Type: Contract
- Announced: 2023-05-16
- Where: Pecém Industrial and Port Complex, Fortaleza, Brazil, Brazil
- Status: under construction
- Capacity: 1.6 GW
- Products: M501JAC gas turbines, peaking power plant
- Sectors: [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md)

## Companies

- [Mitsubishi Power Americas](https://endata.com/companies/9971.md) (supplier)
- [CONSAG](https://endata.com/companies/70324.md) (partner)
- [Portocem Geração de Energia S.A.](https://endata.com/companies/70325.md) (customer)

## Sources

- [business.sherbrookerecord.com](https://business.sherbrookerecord.com/observerreporter/article/bizwire-2023-5-16-mitsubishi-power-to-supply-technology-to-brazils-largest-peaking-power-plant-in-support-of-countrys-energy-transition), 2023-05-16: "Mitsubishi Power will supply four M501JAC enhanced air-cooled gas turbines while CONSAG will be responsible for supplying the balance of plant."

---