# GE and MYTILINEOS to build 200 MW gas-fired reserve power plant for ESB in Dublin

GE Gas Power and MYTILINEOS secured an order from ESB to construct a temporary reserve gas-fired power plant at ESB's North Wall site in Dublin, powered by 6 GE LM2500XPRESS gas turbines with a combined capacity of approximately 200 MW, to be operational before the 2023-24 winter peak.

- Type: Contract
- Announced: 2022-12-19
- Where: Dublin, Ireland
- Status: announced
- Capacity: 200 MW
- Products: gas turbines, LM2500XPRESS, reserve power
- Sectors: [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md)

## Companies

- [GE Gas Power](https://endata.com/companies/7327.md) (supplier)
- [MYTILINEOS](https://endata.com/companies/11336.md) (partner)
- [Electricity Supply Board of Ireland](https://endata.com/companies/45661.md) (customer)

## Sources

- [globalenergyworld.com](https://www.globalenergyworld.com/news/traditional-energy/2022/12/19/ge-mytilineos-supply-approximately-200-mw-reserve-power-electricity-supply-board-ireland-esb), 2022-12-19: "We’re excited to bring temporary power to ESB’s North Wall site before the 2023-24 winter peak demand season to help provide a reliable source of reserve power."

---