# Siemens Energy to supply H2-ready gas turbines for EnBW plant conversion

Siemens Energy signed an agreement with EnBW to supply two 62-MW SGT-800 gas turbines for converting the Stuttgart-Münster coal-fired CHP plant to gas, with hydrogen-ready capability up to 75% H2. The project could be operational by 2026.

- Type: Contract
- Announced: 2022-11-17
- Where: Stuttgart-Münster, Germany, Germany
- Status: announced
- Capacity: 124 MW (two 62-MW turbines)
- Products: SGT-800 gas turbines, hydrogen-ready combustion technology
- Sectors: [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md)

## Companies

- [EnBW](https://endata.com/companies/6785.md) (customer)
- [Siemens Energy](https://endata.com/companies/6803.md) (supplier)

## Sources

- [powermag.com](https://www.powermag.com/siemens-energy-seals-deal-for-hydrogen-ready-coal-to-gas-switch/), 2022-11-17: "Siemens Energy on Nov. 17 sealed an agreement with the utility for an overall package that will ensure all systems at the conversion...to be fueled with hydrogen."

---
Data from Endata (https://endata.com/). Announcements are summarized from public sources and may be incomplete; check the linked originals.