# Keppel awards EPC contract for Singapore's first hydrogen-ready power plant

Keppel Infrastructure reached a final investment decision to develop a 600MW hydrogen-ready CCGT power plant at Sakra, Singapore, and awarded an EPC contract to a consortium of Mitsubishi Power Asia Pacific and Jurong Engineering. The plant costs S$750 million and is expected to be completed in the first half of 2026.

- Type: Contract
- Announced: 2022-09-01
- Where: Sakra, Singapore, Singapore
- Value: $540.0M (750.0M SGD)
- Status: announced
- Capacity: 600 MW
- Products: hydrogen-ready combined cycle gas turbine power plant
- Sectors: [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md)

## Companies

- [Jurong Engineering Limited](https://endata.com/companies/34224.md) (supplier)
- [Keppel Infrastructure](https://endata.com/companies/64106.md) (customer)
- [Mitsubishi Power Asia Pacific](https://endata.com/companies/65044.md) (supplier)

## Sources

- [knowesg.com](https://knowesg.com/finance-technology/mitsubishi-power-asia-pacific-and-jurong-engineering-to-build-singapores-01092022), 2022-09-01: "Keppel Sakra Cogen Plant will be Singapore's first hydrogen-ready power plant."

---
Data from Endata (https://endata.com/). Announcements are summarized from public sources and may be incomplete; check the linked originals.