# Voestalpine completes first phase of control system upgrade with Primetals

Voestalpine completed the first phase of a modernization project for control systems at its Linz steel plant, carried out by Primetals Technologies. The project covers three converter lines and the higher-level converter area, with completion expected by end of 2022. The announcement was made on 5 August 2022.

- Type: Contract
- Announced: 2022-08-05
- Where: Linz, Austria
- Status: under construction
- Products: process control system upgrades
- Sectors: [Industrial Machinery](https://endata.com/sectors/industrial-machinery.md)

## Companies

- [Primetals Technologies](https://endata.com/companies/16384.md) (supplier)
- [voestalpine](https://endata.com/companies/19723.md) (customer)

## Sources

- [gmk.center](https://gmk.center/en/news/primetals-has-completed-the-1st-phase-of-the-control-system-modernization-for-voestalpine/), 2022-08-05: "Primetals is currently upgrading the entire process control system at the Voestalpine steel plant in Linz (Austria)."

---