# Siemens Energy to supply electrical equipment for Equinor Troll West electrification

Siemens Energy received a contract from Aker Solutions to supply electrical transmission, distribution and power management systems for Equinor's Troll West project in the North Sea, which will power Troll B and C from shore via a 150 MW subsea cable. Equinor estimates annual emissions cuts of about 500,000 tonnes.

- Type: Contract
- Announced: 2021-09-09
- Where: Troll field, North Sea, Norway
- Status: announced
- Capacity: 150 MW subsea transmission cable
- Products: transformers, reactors, switchgears, power management system, static frequency converters, large-scale drive trains
- Sectors: [Electrical Equipment](https://endata.com/sectors/electrical-equipment.md), [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md)

## Companies

- [Siemens](https://endata.com/companies/301.md) (partner)
- [Equinor](https://endata.com/companies/1741.md) (customer)
- [Aker Solutions](https://endata.com/companies/1742.md) (customer)
- [Siemens Energy](https://endata.com/companies/6803.md) (supplier)

## Sources

- [siemens-energy.com](https://www.siemens-energy.com/global/en/home/press-releases/power-shore-solution-will-help-equinor-reduce-offshore-platform-emissions-north-sea.html), 2021-09-09: "Siemens Energy received a contract from Aker Solutions to supply the complete packages for the electrical transmission, distribution, and power management system (PMS) for the Troll West electrification project in the North Sea."

---