# Siemens Energy-led consortium awarded EPC contract for 881 MW CCGT unit in Ostiglia

The RTI consortium of Siemens Energy, Fata and Demont was awarded an EPC/turnkey contract for the engineering, procurement and construction of a new 881 MW combined cycle gas turbine unit at the Ostiglia power plant in Italy.

- Type: Contract
- Announced: 2022-04-19
- Where: Ostiglia, Italy
- Status: announced
- Capacity: 881 MW
- Products: combined cycle gas turbine unit, H-class gas turbine, heat recovery steam generator, steam turbine
- Sectors: [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md)

## Companies

- [Siemens Energy](https://endata.com/companies/6803.md) (partner)
- [Demont](https://endata.com/companies/53246.md) (partner)
- [Fata S.p.A.](https://endata.com/companies/54273.md) (partner)
- [EP Produzione](https://endata.com/companies/59348.md) (customer)

## Sources

- [demont.it](https://www.demont.it/activities/epc-news-en/power-generation-epc-en-news/siemens-fata-demont-together/), 2022-04-19: "the RTI Siemens Energy, Fata and Demont S.r.l. was awarded the EPC/Turnkey Contract relating to the Engineering, Procurement and Construction of a new CCGT unit in Ostiglia Power Plant"

---