# South Field Energy natural gas plant achieves commercial operation in Ohio

The 1,182 MW South Field Energy combined cycle natural gas power plant in Wellsville, Ohio, managed by Advanced Power and built by Bechtel, achieved commercial operation. GE provided the H-Class full combined cycle plant solution.

- Type: Expansion
- Announced: 2021-10-13
- Where: Wellsville, Ohio, United States
- Starts operating: 13 Oct 2021
- Status: completed
- Capacity: 1182 MW
- Products: natural gas power plant, 7HA.02 gas turbine, STF-D650 steam turbine
- Sectors: [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md)

## Companies

- [Advanced Power](https://endata.com/companies/21719.md)
- [GE](https://endata.com/companies/1022.md) (supplier)
- [Bechtel](https://endata.com/companies/2657.md) (partner)

## Sources

- [gevernova.com](https://www.gevernova.com/news/press-releases/powered-by-ges-ha-technology-south-field-energy-in-wellsville-ohio-adds-1-gigawatt), 2021-10-13: "South Field Energy is Advanced Power’s third major infrastructure project in the United States and we are proud that a leading energy development company of their caliber has once again selected GE as their partner of choice."

---
Data from Endata (https://endata.com/). Announcements are summarized from public sources and may be incomplete; check the linked originals.