Saskatchewan Power Corporation (SaskPower) is developing the 350MW Great Plains combined-cycle natural gas-fired power plant near Moose Jaw, Saskatchewan, with an estimated investment of C$825 million ($504 million). Construction started in March 2021 and commissioning is expected in August 2024.

- Type: New facility
- Announced: 2021-08-09
- Where: Moose Jaw, Saskatchewan, Canada
- Value: $504.0M (825.0M CAD)
- Starts operating: 1 Aug 2024
- Status: under construction
- Capacity: 350 MW
- Products: electricity
- Sectors: [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md)

## Companies

- [Saskatchewan Power Corporation](https://endata.com/companies/23478.md)

## Sources

- [nsenergybusiness.com](https://www.nsenergybusiness.com/projects/great-plains-combined-cycle-power-project/), 2021-08-09: "The Great Plains power project, also known as the Moose Jaw power project, is a 350MW combined-cycle natural gas-fired power plant under construction in the Saskatchewan province, Canada."

---