# Edison Group refurbishing Marghera Levante power plant

Edison Group is refurbishing the 766MW Marghera Levante gas-fired power plant in Porto Marghera, Venice, with a new 780MW combined-cycle unit, costing approximately €350 million. The project started in 2019 and is expected to be completed in 2022.

- Type: Expansion
- Announced: 2021-07-16
- Where: Porto Marghera, Venice, Italy
- Value: $412.0M (350.0M EUR)
- Starts operating: 2022
- Status: under construction
- Capacity: 780MW
- Products: gas-fired combined-cycle power
- Sectors: [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md)

## Companies

- [Edison](https://endata.com/companies/37790.md)

## Sources

- [nsenergybusiness.com](https://www.nsenergybusiness.com/projects/marghera-levante-power-plant-refurbishment/), 2021-07-16: "The refurbishment project being undertaken by the plant owner and operator Edison Group is estimated to cost approximately £266m (€350m)."

---
Data from Endata (https://endata.com/). Announcements are summarized from public sources and may be incomplete; check the linked originals.