Indonesia Power is developing the 780MW Tambak Lorok block-3 gas-fired combined-cycle power plant in Semarang, Central Java, Indonesia, with construction started in February 2018.

- Type: New facility
- Announced: 2021-06-09
- Where: Semarang, Central Java, Indonesia
- Status: under construction
- Capacity: 780 MW
- Products: electricity
- Sectors: [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md)

## Companies

- [Indonesia Power](https://endata.com/companies/25717.md)
- [General Electric](https://endata.com/companies/1262.md) (supplier)

## Sources

- [nsenergybusiness.com](https://www.nsenergybusiness.com/projects/tambak-lorok-combined-cycle-power-plant-block-3/), 2021-06-09: "The main civil construction works on the power project were started in February 2018."

---