# Tubli wastewater plant completes concrete restoration of aeration basins

Bahrain's Works Ministry completed concrete restoration works of the aeration basins at the Tubli wastewater plant, costing BD 1,620,308. The project strengthened structures and increased plant capacity.

- Type: Expansion
- Announced: 2021-04-30
- Where: Tubli, Bahrain
- Value: $4.30M (1.62M BHD)
- Starts operating: 30 Apr 2021
- Status: completed
- Products: wastewater treatment
- Sectors: [Water Treatment Equipment](https://endata.com/sectors/water-treatment-equipment.md)

## Companies

- [Ministry of Works, Bahrain](https://endata.com/companies/36297.md)
- [Kooheji Technical Services](https://endata.com/companies/54806.md) (supplier)

## Sources

- [newsofbahrain.com](https://www.newsofbahrain.com/bahrain/72097.html), 2021-04-30: "the BD 1,620,308 restoration works contributed to strengthening the concrete structures and raise the plants capacity to deal with the increased flow of wastewater."

---
Data from Endata (https://endata.com/). Announcements are summarized from public sources and may be incomplete; check the linked originals.