# Voith Hydro delivers stator for Töging power plant upgrade

Voith Hydro transported a 105-ton, 8.2-meter diameter stator to the Töging am Inn power plant in Bavaria, part of a contract to supply three 55-MVA generators for the plant's renewal project by operator VERBUND.

- Type: Contract
- Announced: 2021-04-07
- Where: Töging am Inn, Bavaria, Germany
- Status: completed
- Capacity: three 55-MVA generators
- Products: stator for hydroelectric generator
- Sectors: [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md)

## Companies

- [Voith Hydro](https://endata.com/companies/10534.md)
- [VERBUND](https://endata.com/companies/54286.md) (customer)

## Sources

- [voith.com](https://www.voith.com/corp-de/news-room/press-releases/2021-04-07-vh-voith-hydro-transportiert-gigantischen-stator-nach-bayern.html), 2021-04-07: "Voith Hydro transportiert gigantischen Stator nach Bayern - Bislang breitester Transport in der Geschichte von Voith Hydro Heidenheim verlässt das Werksgelände."

---