# SK E&C wins engineering contract for Equinix SOFC plant

SK E&C won an engineering, procurement and execution project at Equinix to construct a 6.4 MW SOFC plant at a data center in San Jose, California. Groundbreaking is scheduled for April 2021.

- Type: Contract
- Announced: 2021-02-04
- Where: San Jose, California, United States
- Status: announced
- Capacity: 6.4 MW
- Products: SOFC plant
- Sectors: [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md)

## Companies

- [SK E&C](https://endata.com/companies/29784.md) (supplier)
- [Equinix](https://endata.com/companies/53064.md) (customer)

## Sources

- [korea-certification.com](https://www.korea-certification.com/en/sk-ec-begins-production-of-environmentally-friendly-fuel-cells/), 2021-02-04: "Groundbreaking is scheduled for April 2021, with commissioning eight months after completion of construction."

---