# Andritz Hydro wins rehab contract for Jebba hydropower plant unit

Mainstream Energy Solutions Ltd awarded Andritz Hydro a contract for the integral rehabilitation of generating unit 2G6 at the Jebba Hydropower Plant in Nigeria. The two-year project includes full rehabilitation of the intake gate, turbine, generator and auxiliary systems.

- Type: Contract
- Announced: 2020-12-11
- Where: North-Central Nigeria, Niger River, 103km downstream of Kainji Dam, Nigeria
- Status: announced
- Products: hydropower turbine rehabilitation, generator rehabilitation, digital turbine governor, excitation system, unit control system, main step-up transformer
- Sectors: [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md)

## Companies

- [Andritz Hydro](https://endata.com/companies/652.md) (supplier)
- [Mainstream Energy Solutions Ltd](https://endata.com/companies/51804.md) (customer)

## Sources

- [waterpowermagazine.com](https://www.waterpowermagazine.com/news/generating-unit-undergoing-rehab-at-jebba-hydro-plant-further-work-planned-8405385/), 2020-12-11: "Mainstream Energy Solutions Ltd (MESL), the concessionaire company of Jebba Hydropower Plant in Nigeria, has awarded Andritz Hydro a contract for the integral rehabilitation of generating unit 2G6 at the key power plant."

---