# Siemens Energy to supply gas turbines for Leipzig district heating plant

Siemens Energy will supply two SGT-800 gas turbine packages for Stadtwerke Leipzig's new combined heat and power plant in Leipzig Süd. The plant, with 125 MW electrical and 163 MW thermal capacity, is scheduled for commissioning at the end of 2022 and will eventually run on green hydrogen.

- Type: Contract
- Announced: 2020-11-19
- Where: Leipzig, Germany, Germany
- Status: announced
- Capacity: 125 MW electrical, 163 MW thermal
- Products: SGT-800 gas turbines, SGen-100A generators, SIESTART battery solution
- Sectors: [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md)

## Companies

- [Siemens Energy](https://endata.com/companies/6803.md) (supplier)
- [Stadtwerke Leipzig](https://endata.com/companies/51332.md) (customer)

## Sources

- [energyglobal.com](https://www.energyglobal.com/other-renewables/19112020/siemens-energy-to-supply-gas-turbines-for-german-climate-neutral-power-project/), 2020-11-19: "The long-term goal is to operate the facility with 100 % hydrogen."

---