# ANDRITZ selected by Hydro-Québec to re-equip Carillon generating station

Hydro-Québec awarded ANDRITZ a contract to supply and install six turbine-generator units at the Carillon generating station on the Ottawa River, Canada, with potential to re-equip all 14 units. The project spans 16 years with last unit commissioning planned for 2036.

- Type: Contract
- Announced: 2020-09-30
- Where: Ottawa River, Quebec, Canada
- Status: announced
- Products: turbine-generator units, Kaplan turbines, speed governors
- Sectors: [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md)

## Companies

- [ANDRITZ](https://endata.com/companies/2007.md) (supplier)
- [Hydro-Québec](https://endata.com/companies/3478.md) (customer)

## Sources

- [newswire.ca](https://www.newswire.ca/fr/news-releases/andritz-selected-for-the-furbishment-of-the-carillon-generating-station-canada-802380135.html), 2020-10-21: "ANDRITZ has been selected by Hydro-Québec as the exclusive partner to re-equip potentially up to all fourteen 54-MW turbine generator units at the Carillon generating station."

---