# Power Machines ships equipment for Cheboksarskaya HPP unit No. 6

Power Machines manufactured and completed shipment of generating equipment for unit No. 6 of the Cheboksarskaya hydropower plant. Unit No. 4 at the project is set to be commissioned in October 2020.

- Type: Expansion
- Announced: 2020-10-05
- Where: Cheboksarskaya hydropower plant, Russia
- Starts operating: Oct 2020
- Status: under construction
- Products: generating equipment for hydropower plant
- Sectors: [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md)

## Companies

- [Power Machines](https://endata.com/companies/15083.md)

## Sources

- [waterpowermagazine.com](https://www.waterpowermagazine.com/news/equipment-shipped-and-unit-due-for-commissioning-at-cheboksarskaya-plant-russia-8163958/), 2020-10-05: "Power Machines has announced it has manufactured and completed the shipment of generating equipment for unit No. 6 of the Cheboksarskaya hydropower plant, with unit No. 4 at the project set to be commissioned this month."

---
Data from Endata (https://endata.com/). Announcements are summarized from public sources and may be incomplete; check the linked originals.