# Duyen Hai 3 coal-fired power plant extension begins commercial operations in Vietnam

The 688MW Duyen Hai 3 coal-fired power plant extension in Tra Vinh province, Vietnam, developed by Power Generation Corporation 1 (EVNGENCO1) with an investment of £680m ($1.08bn), commenced commercial operations in May 2020. Construction started in December 2014.

- Type: Expansion
- Announced: 2020-08-28
- Where: Duyen Hai, Tra Vinh, Vietnam
- Value: $1.08B
- Starts operating: May 2020
- Status: completed
- Capacity: 688MW
- Products: electricity
- Sectors: [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md)

## Companies

- [Power Generation Corporation 1](https://endata.com/companies/49567.md)
- [Toshiba](https://endata.com/companies/8893.md) (supplier)