# Dogger Bank Wind Farm and Seaway7 complete all foundation installations

Dogger Bank Wind Farm and delivery partner Seaway7 installed all 277 transition pieces on the Dogger Bank Wind Farm, marking completion of all foundation installation work on the 3-phase offshore wind project in the North Sea.

- Type: Expansion
- Announced: 2020-08-10
- Where: North Sea, United Kingdom
- Starts operating: 27 Nov 2025
- Status: completed
- Products: transition pieces
- Sectors: [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md)

## Companies

- [Seaway7](https://endata.com/companies/18655.md) (partner)
- [Dogger Bank Wind Farm](https://endata.com/companies/49054.md) (customer)

## Sources

- [seaway7.com](https://www.seaway7.com/media/company-news/), 2020-08-10: "Dogger Bank Wind Farm and delivery partner Seaway7 have installed all 277 transition pieces on Dogger Bank Wind Farm, marking the completion of all foundation installation work."

---