# Archer Western and Brown and Caldwell begin expansion of Big Creek Water Reclamation Facility

Construction began on a $300 million expansion of the Big Creek Water Reclamation Facility in Roswell, Georgia, from 24 MGD to 32 MGD. The project is delivered by a joint venture of Archer Western and Brown and Caldwell for Fulton County.

- Type: Expansion
- Announced: 2020-07-30
- Where: Roswell, Georgia, United States
- Value: $300.0M
- Starts operating: 2024
- Status: under construction
- Capacity: 32 million gallons per day
- Products: water reclamation services
- Sectors: [Water Treatment Equipment](https://endata.com/sectors/water-treatment-equipment.md)

## Companies

- [Archer Western](https://endata.com/companies/21538.md)
- [Brown & Caldwell](https://endata.com/companies/26414.md) (partner)
- [Fulton County Department of Public Works](https://endata.com/companies/48984.md) (customer)

## Sources

- [waterworld.com](https://www.waterworld.com/water-reuse/article/14180724/archer-western-brown-and-caldwell-begin-expansion-of-big-creek-water-reclamation-facility), 2020-07-30: "Construction of large-scale expansions to the Big Creek Water Reclamation Facility in Roswell, Georgia, is officially underway"

---