# Sinopec Yizheng starts up meltblown fabric production line

Sinopec Yizheng Chemical Fiber started up a 500-tonne-per-year meltblown fabric production line on March 29, 2020, after 35 days of construction. The line has over 95% domestic equipment, and 16 lines are expected to be fully operational by May 2020.

- Type: New facility
- Announced: 2020-03-31
- Where: Yizheng, Jiangsu, China
- Starts operating: 29 Mar 2020
- Status: completed
- Capacity: 500 tonnes per year
- Products: meltblown fabric
- Sectors: [Specialty Chemicals](https://endata.com/sectors/specialty-chemicals.md)

## Companies

- [Sinopec Yizheng Chemical Fiber](https://endata.com/companies/46213.md)

## Sources

- [workercn.cn](https://www.workercn.cn/papers/grrb/2020/03/31/6/news-4.html), 2020-03-31: "该项目国产化率达95%以上，把常规一年的建设周期压缩成一个多月，跑出了中国制造的加速度。"

---