# GE-led consortium to build 1.4 GW gas power units at Dolna Odra

GE announced an order to supply two 9HA.01 gas turbines, steam turbines, generators and HRSGs for a 1.4 GW combined cycle power plant at PGE's Dolna Odra site in Poland, with commissioning expected in 2023.

- Type: Contract
- Announced: 2020-03-30
- Where: Western Pomerania region, Poland
- Status: announced
- Capacity: 1.4 GW
- Products: gas turbines, steam turbines, generators, HRSGs for combined cycle power plant
- Sectors: [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md)

## Companies

- [GE](https://endata.com/companies/1022.md) (supplier)
- [Polska Grupa Energetyczna](https://endata.com/companies/46190.md) (customer)

## Sources

- [ge.com](https://www.ge.com/news/press-releases/ge-led-consortium-build-two-high-efficiency-lower-emission-ha-combined-cycle-power), 2020-03-30: "GE today announced the order of two high-efficiency and lower emission power units to be constructed through consortium at the Polska Grupa Energetyczna Górnictwo i Energetyka Konwencjonalna’s (PGE) Dolna Odra Power Plant."

---