# Burns & McDonnell selected for $134M control system upgrade at Robert Moses Niagara Power Plant

Burns & McDonnell was selected as EPC contractor by the New York Power Authority for a $134 million electrical control system modernization at the 2,525-MW Robert Moses Niagara Power Plant, part of a $1.1 billion Next Generation Niagara program.

- Type: Contract
- Announced: 2020-01-23
- Where: Niagara Falls, New York, United States
- Value: $134.0M
- Status: announced
- Products: control system upgrade, Ovation automation system
- Sectors: [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md)

## Companies

- [Emerson](https://endata.com/companies/355.md) (supplier)
- [Burns & McDonnell](https://endata.com/companies/10373.md) (partner)
- [New York Power Authority](https://endata.com/companies/38306.md) (customer)

## Sources

- [prnewswire.com](https://www.prnewswire.com/news-releases/burns--mcdonnell-selected-by-nypa-for-major-control-system-modernization-project-at-one-of-largest-hydropower-facilities-in-north-america-300991652.html), 2020-01-23: "The control systems upgrade is a key piece of the puzzle as we ready the Niagara Power Project for another 50 years of service."

---
Data from Endata (https://endata.com/). Announcements are summarized from public sources and may be incomplete; check the linked originals.