# Polimex Mostostal contracts Siemens for steam turbine generator set

Polimex Mostostal has signed an agreement with Siemens AG for the production and delivery of a steam turbine generator set, feed water heaters and spare parts for a coal-fired power unit in Puławy, Poland. The contract value is PLN 17.457 million net, with last delivery scheduled for 15 September 2021.

- Type: Contract
- Announced: 2019-12-20
- Where: Puławy, Poland
- Value: $4.50M (17.5M PLN)
- Status: announced
- Capacity: 1,400 MW
- Products: steam turbine generator set, feed water heaters, spare parts
- Sectors: [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md)

## Companies

- [Polimex-Mostostal](https://endata.com/companies/24324.md)
- [Siemens](https://endata.com/companies/301.md) (supplier)
- [General Electric](https://endata.com/companies/1262.md) (partner)
- [PGE](https://endata.com/companies/22192.md) (customer)
- [PGE Górnictwo i Energetyka Konwencjonalna](https://endata.com/companies/44397.md) (customer)
- [General Electric Global Services](https://endata.com/companies/44869.md) (partner)
- [General Electric International](https://endata.com/companies/44870.md) (partner)

## Sources

- [polimex-mostostal.pl](https://www.polimex-mostostal.pl/en/report/conclusion-significant-agreement-issuer-2), 2019-12-20: "The subject of the Agreement is the production and delivery by the Contractor of a steam turbine generator set, feed water heaters and spare parts for the purpose of the 'Construction of a coal-fired power unit in Puławy'."
- [polimex-mostostal.pl](https://www.polimex-mostostal.pl/en/report/conclusion-significant-agreement-issuer-4), 2020-01-30: "The subject of the Agreement is a turnkey construction of two gas and steam power units (number 9 and 10, provision of complete sets of power generating equipment and their auxiliary installations and any other technological, mechanical, electrical and automation installations, along with associated"
- [polimex-mostostal.pl](https://www.polimex-mostostal.pl/en/news/new-contract-construction-two-gas-and-steam-power-units-total-capacity-approximately-1400-mw), 2020-02-03: "The contract signing ceremony for the construction of two modern, high-performance and low-carbon generating units at the Dolna Odra Power Plant that took place on 30 January 2020"

---