# Siemens wins turnkey contract for Mirfa grid substation in Abu Dhabi

Siemens was awarded a turnkey contract by TRANSCO to supply, install and hand over a 400/220/33-kV high-voltage grid substation at Mirfa, Abu Dhabi, connecting the new Mirfa Power Plant to the grid.

- Type: Contract
- Announced: 2019-09-25
- Where: Mirfa, Abu Dhabi, United Arab Emirates
- Status: announced
- Capacity: 400/220/33-kV grid substation
- Products: gas-insulated switchgear, 500MVA and 100MVA transformers, reactors
- Sectors: [Electrical Equipment](https://endata.com/sectors/electrical-equipment.md)

## Companies

- [Siemens](https://endata.com/companies/301.md) (supplier)
- [Abu Dhabi Transmission and Despatch Company (TRANSCO)](https://endata.com/companies/5590.md) (customer)

## Sources

- [press.siemens.com](https://press.siemens.com/middleeast/en/pressrelease/siemens-help-enhance-abu-dhabi-power-supply-high-voltage-substation-mirfa), 2019-09-25: "Siemens ... has been awarded a turnkey contract by the Abu Dhabi Transmission and Despatch Company, known as TRANSCO, to supply a high-voltage grid substation at Mirfa in Abu Dhabi."

---