# NESMA Electric awarded $21.2 million substation contract by Saudi Electricity Company

NESMA Electric, a subsidiary of NESMA Holding, signed a SAR 79.9 million ($21.2 million) contract with Saudi Electricity Company to build the Arafat-3 110/13.8kV substation in Makkah, Saudi Arabia. The project has a 25-month completion period.

- Type: Contract
- Announced: 2019-09-17
- Where: Arafat, Makkah, Saudi Arabia
- Value: $21.2M
- Status: announced
- Products: 110/13.8kV substation, GIS, power transformers, switchgear
- Sectors: [Electrical Equipment](https://endata.com/sectors/electrical-equipment.md)

## Companies

- [Saudi Electricity Company](https://endata.com/companies/8447.md) (customer)
- [NESMA Electric](https://endata.com/companies/42160.md) (supplier)

## Sources

- [saudigulfprojects.com](https://www.saudigulfprojects.com/2019/09/nesma-secured-a-deal-of-21-2-million-for-110-13-8kv-substation-in-makkah/), 2019-09-17: "The project aims to meet the expected increase in population and pilgrims in Makkah."

---