# Siemens Gamesa conditionally awarded 880 MW Sunrise Wind offshore turbine order

Siemens Gamesa was conditionally awarded a contract to supply SG 8.0-167 DD offshore wind turbines totaling 880 MW for the Sunrise Wind project off New York, with a service agreement included. The project is expected to be operational in 2024.

- Type: Contract
- Announced: 2019-09-15
- Where: Federal waters about 30 miles off Montauk Point, New York, United States
- Status: announced
- Capacity: 880 MW
- Products: SG 8.0-167 DD offshore wind turbines, service agreement
- Sectors: [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md)

## Companies

- [Siemens Gamesa Renewable Energy](https://endata.com/companies/3169.md) (supplier)
- [Ørsted](https://endata.com/companies/3516.md) (customer)
- [Eversource](https://endata.com/companies/5547.md) (customer)

## Sources

- [windsystemsmag.com](https://www.windsystemsmag.com/siemens-gamesa-awarded-largest-u-s-offshore-order-to-date/), 2019-09-15: "Siemens Gamesa has been conditionally awarded the contract to deliver offshore wind turbines totaling 880 MW for the Sunrise Wind project."

---
Data from Endata (https://endata.com/). Announcements are summarized from public sources and may be incomplete; check the linked originals.