# Doosan Heavy wins $100.6M boiler and turbine order for Indonesia's Palu 3 power plant

Doosan Heavy Industries & Construction won a 120 billion won (about $100.6 million) order from PLN to supply CFB boilers and turbines for the 110 MW Palu 3 thermal power plant on Sulawesi, with installation planned by 2023. The deal was announced on 9 September 2019.

- Type: Contract
- Announced: 2019-09-09
- Where: Palu, Sulawesi, Indonesia
- Value: $100.6M (120.0B KRW)
- Status: announced
- Capacity: 110 MW
- Products: CFB boilers, turbines
- Sectors: [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md)

## Companies

- [Doosan Heavy Industries & Construction](https://endata.com/companies/997.md) (supplier)
- [Perusahaan Listrik Negara (PLN)](https://endata.com/companies/5507.md) (customer)

## Sources

- [pulse.mk.co.kr](https://pulse.mk.co.kr/news/all/8974254), 2019-09-09: "Under the deal signed with Indonesia's state-run electricity provider Perusahaan Listrik Negara (PLN), Doosan Heavy Industries & Construction will supply circulating fluidized bed (CFB) boilers and turbines for the Palu 3 thermal power plant."

---