# Toshiba wins contract to retrofit steam turbines and generators at Mt Piper Power Station

Toshiba Energy Systems & Solutions, through its Australian subsidiary, has won a major contract to retrofit steam turbines, generators, and associated equipment for EnergyAustralia's Mt Piper Power Station in Portland, Australia. The project will increase output from 1400MW to 1460MW without increasing coal consumption or emissions, and is scheduled to be completed by the end of 2021.

- Type: Contract
- Announced: 2019-07-08
- Where: Portland, Australia, Australia
- Status: announced
- Capacity: increase output from 1400MW to 1460MW
- Products: steam turbines, generators, heat exchangers
- Sectors: [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md)

## Companies

- [Toshiba Energy Systems & Solutions](https://endata.com/companies/4554.md) (supplier)
- [EnergyAustralia](https://endata.com/companies/28544.md) (customer)
- [Toshiba International Corporation](https://endata.com/companies/30556.md) (supplier)

## Sources

- [global.toshiba](https://www.global.toshiba/ww/news/energy/2019/07/news-20190708-01.html), 2019-07-08: "Toshiba ESS today announced that its Australian subsidiary has won a major contract to retrofit steam turbines, generators, and associated equipment as part of the modernization project of EnergyAustralia’s Mt Piper Power Station."

---
Data from Endata (https://endata.com/). Announcements are summarized from public sources and may be incomplete; check the linked originals.