# Alex Fraser opens asphalt and glass recycling plants in Laverton North

Alex Fraser opened a high recycled technology asphalt plant and a glass recycling plant at its integrated recycling facility in Laverton North, Victoria, with a $20 million investment, capable of producing 800 tonnes of construction sand per day and over half a million tonnes of green asphalt per year.

- Type: New facility
- Announced: 2019-05-31
- Where: Laverton North, Victoria, Australia
- Value: $13.8M (20.0M AUD)
- Starts operating: 31 May 2019
- Status: completed
- Capacity: 800 tonnes of construction sand per day; over 500,000 tonnes of green asphalt per year
- Products: recycled asphalt, construction sand from glass
- Sectors: [Construction Materials](https://endata.com/sectors/construction-materials.md)

## Companies

- [Alex Fraser Group](https://endata.com/companies/29752.md)

## Sources

- [alexfraser.com.au](https://alexfraser.com.au/an-exciting-development-for-victorias-circular-economy/), 2019-05-31: "These new $20 million facilities are part of Alex Fraser's long term investment in improving resource recovery and infrastructure sustainability for Victoria"

---
Data from Endata (https://endata.com/). Announcements are summarized from public sources and may be incomplete; check the linked originals.