# Outotec wins €15M paste backfill system contract for Prominent Hill

Outotec won a €15 million contract to design and deliver a mine paste backfill system to Prominent Hill, with a capacity of 215 m³/hour.

- Type: Contract
- Announced: 2019-05-15
- Where: Australia
- Value: $16.8M (15.0M EUR)
- Status: announced
- Capacity: 215 m³/hour
- Products: paste backfill system
- Sectors: [Mining Equipment](https://endata.com/sectors/mining-equipment.md)

## Companies

- [Outotec](https://endata.com/companies/776.md)
- [Prominent Hill](https://endata.com/companies/39409.md) (customer)

## Sources

- [miningmagazine.com](https://www.miningmagazine.com/processing/news/1363112/outotec-paste-backfill-prominent-hill), 2019-05-15: "A reliable paste backfill system is critical to the whole mine and its operations."

---