# Ansaldo Energia signs contract with Edison for GT36 gas turbine at Marghera

Edison and Ansaldo Energia signed a contract for a new combined-cycle gas turbine plant at Marghera Levante, Italy. The investment is over €300 million, and the plant will use Ansaldo's GT36 gas turbine, achieving 780 MW capacity and 63% efficiency.

- Type: Contract
- Announced: 2019-03-12
- Where: Marghera Levante, Venice, Italy
- Value: $340.0M (300.0M EUR)
- Status: announced
- Capacity: 780 MW
- Products: GT36 gas turbine, combined-cycle power plant
- Sectors: [Power Generation Equipment](https://endata.com/sectors/power-generation-equipment.md)

## Companies

- [Ansaldo Energia](https://endata.com/companies/5573.md) (supplier)
- [Edison](https://endata.com/companies/37790.md) (customer)

## Sources

- [turbomachinerymag.com](https://www.turbomachinerymag.com/view/edison-and-ansaldo-energia-announce-an-agreement-that-will-make-the-thermoelectric-power-plant-of-porto-marghera-the-most-eficient-in-europe), 2019-03-12: "The contract signed today will have at least three major benefits: commercial, technological, and returning to work in Italy after at least a decade."

---
Data from Endata (https://endata.com/). Announcements are summarized from public sources and may be incomplete; check the linked originals.